We were looking for an affordable home in southeastern Ontario with deep energy retrofit potential when we found this charming wartime bungalow. We wanted to do the job right in order to avoid costly rework in the future, but our budget would not allow us to undertake the entire project at once. Working with a deep retrofit expert, we have developed a manageable, staged approach where each of the stages took into account the other work that would need to be done.
When we first looked at the house, we found it was in good shape overall, but had a very old furnace and air conditioning unit, minimal insulation, and old windows. Aesthetically, it was outdated but had original wood floors and other charming features. We thought it had great potential for both a retrofit to make it energy efficient and DIY renovation work to make it more liveable and attractive. It was appealing that not a lot had been done to it, meaning that we wouldn’t have to pay for or redo piecemeal upgrades that had been done before.
After moving in, we tested the vermiculite attic insulation and learned it contained asbestos, which would require remediation before we could add new insulation. We also noticed that the basement was quite cold in the winter and had some moisture issues, leading us to prioritize the foundation phase of the retrofit.
Next, we hired Homesol Building Solutions to perform an energy audit. The audit showed where the biggest savings could be achieved. Because we were determined to get to net zero and are on a limited budget, we knew we had to get everything we did right - on the first try and as efficiently as possible. Our adviser used the energy audit to dial in the best set of net zero-ready energy specifications for the whole house that also took into account how the house was when we started. (See Before and After specs).
The next step was to develop a plan where we could retrofit our house in affordable stages while meeting the net-zero specifications. The advisor helped us come up with a plan that accounts for later stages so that we will never have to undo or take apart previous work. Stage 2 - The Attic (below) shows the kind of thinking that’s needed.
Since we were eager to address the basement moisture issues as soon as possible, we decided to tackle the foundation insulation first and add a waterproofing membrane and weeping tile as part of the same excavation project.
The original plan was to make the house as efficient as possible before adding a heat pump. We would do most of the upgrades, the foundation, the attic, and then upgrade the exterior wall insulation and windows before doing the mechanical needed to electrify the home.
However, because our air conditioning died in late 2023, we decided to do the mechanical after completing the basement walls and attic, because these were the largest sources of heat loss.
Because the cold climate heat pump is sized for the full retrofit, we may have some issues in the very coldest weather. So until we do the exterior walls and windows, we will keep a couple of electric heaters handy.
Finally, at stage five, we will add rooftop solar.
This staged approach allowed us to address immediate issues with the structure and was flexible enough to account for unforeseen developments like the air conditioning unit giving out. Most importantly, it provided a clear, practical order of operations that will get us to net-zero.
It made sense to do the basement first. The basement accounted for the biggest portion of the building’s annual heat loss (around 30%). It was cold and uncomfortable. (We work from home and spend a lot of time in our basement office.) It also leaked in two places. The steps in this phase included:
1 Excavating to the footings, inspecting the foundation,sealing any cracks, and applying new waterproofing.
2 Installing new weeping tile and sump.
3 Installing low global warming potential (GWP) styrofoam insulation to R24.
4 Replacing basement windows with triple-glazed, LOW‑E Argon-filled windows, and adding window wells so the grade could be raised for better drainage.
5 Providing for an air-tight connection to the wall air barrier to be installed in Phase 3.
6 Adding temporary flashing over the new insulation to keep the water out until after the upper walls could be done.
7 Removing the old, asphalt driveway. To be replaced with a small driveway later, reclaiming more space for the backyard.
8 Regrading around the entire foundation (will be completed in Spring 2024, after the ground has had a chance to settle)
The Energuide Report showed the heat loss through the attic was about 15% of the total - not including attic air leakage. There is about 5” of old vermiculite insulation which testing shows contains some asbestos and a few scattered fibreglass insulation batts. The attic is also very likely to be responsible for a lot of the air leakage. (We were unable to test the actual air leakage for fear of sucking vermiculite into the house.) The steps in the phase:
Before efficiency upgrades, space heating alone accounted for 54% of the house’s estimated annual energy use and water heating for 21%. The steps in this phase, which was moved up because the home’s air conditioning unit died, will include:
The main walls account for over 20% of the building’s annual heat loss. The steps in this phase will include:
Click to view larger images