Highlands Panelized Deep Retrofit

Jim Sandercock and Melanie Harmsma's retrofit was the first panelized, Energiesprong-inspired deep retrofit in North America.

No items found.
No items found.
Building photo: Front of home, post panel installation with new veranda
Building photo: Front of home, pre-retrofit

Edmonton, Alberta

Inspired by a technique out of the Netherlands called Energiesprong, a panelized retrofit uses cutting-edge imaging technology to design pre-built panels. These airtight, super-insulated panels are built off-site and attached to the outside of existing buildings. After they are installed, the building is airtight, way more comfortable and able to get all of its energy from renewables.

Working with Butterwick Projects, the builder that managed the retrofit, Logan Gilmour, a software developer from the gaming world, digitally captured the dimensions of this 1,950-square-foot 1951 home with a drone and his custom photogrammetry software.

Peter Amerongen, one of Retrofit Canada's co-founders and a partner at Butterwick Project, used Logan’s 3D models to design the pre-built panels.

To get the house ready for the panel installation crews had to:

  • Use a hydrovac truck to cut a slot around the house so crews could drop in a 5.5” sheet of graphite-infused EPS insulation (R25).
  • Install pressure-treated rockwool-insulated panel support box (R28) with penetrations for new HRV and Air source Heat pump and existing services.
  • Loosen the existing windows that were going to be replaced. The home did have a number of high-performance windows that did not require replacement.
  • Temporarily remove previously installed solar modules.
  • Install the tie-back blocks that the panels would be attached to.

When the panels were built and delivered, Butterwick crews worked with a spider crane operator to install them. All the panels were installed in less than a day and fit beautifully, within the design tolerances. The new windows were factory-installed to reduce disruptions for the owners.

After the panel installation, crews:

  • Installed the tie-back straps to secure the panels in place.
  • Sealed the water-resistive barrier (WRB)  from panel to panel and the panel support box.
  • Wrapped the entire existing roof for air tightness.
  • Framed a new roof over the existing roof and insulated it with Roxul insulation (R38).
  • Removed the old windows and finished the window extensions on the inside.
  • Added the new traditional veranda.
  • Installed siding and the finishing touches that fit in with the architectural character of the neighbourhood.
  • Replaced the gas furnace and hot water tank with Air Source Heat Pumps and disconnect the gas line.
  • Installed a high-efficiency Heat Recovery Ventilator that will provide a continuous supply of healthy fresh air.
  • Reinstalled the solar modules on the house and additional modules on the garage that will produce as much energy as the house needs for heating, hot water and everything else.

What went well?

Since the panel installation, the family has noticed the house is quieter and less drafty. More importantly, where the house was prone to upstairs overheating in the summer and was way too cold in the basement in the winter, the temperature has evened out.

"In September 2022, we had a late-summer heat wave, with temperatures over 30 degrees celsius," said Sandercock. "And this was before we had the new ventilation and cooling systems, but the upstairs was completely fine. And then in December, there was a cold snap with -30 celsius temperatures, and our heat pump managed the demand without the auxiliary heat needing to kick in."

Butterwick and Jim will be doing ongoing monitoring of the retrofit's energy performance. But Jim had already noted that when their power demands on the grid went up during that cold snap, their total utility bill was lower thanks to the savings from being disconnected from natural gas.

Amerongen said, “‍We were happy with how much on-site labour the pre-built panels saved and how well they fit. Using the old chimney chase and attic space to run the new HRV exhaust lines also meant there was very little inside repair work.”

He was also happy with the “nifty way” Butterwick insulated and air sealed under the back entry laparoscopically.

Challenges

Sandercock and Butterwick did experience some challenges. This is unsurprising given this was the first single-family home project like this on the continent - there was always going to be a learning curve.

These are some of the challenges:

  • Supply chain issues and inflation related to the Covid-19 pandemic resulted in record costs for lumber.
  • Project management was complicated even with a panelized approach that required less labour and demolition. The home had solar installed before the retrofit. Butterwick had to remove this in spring 2022 and reinstall the system and some new modules in late fall. The interval between removal and reinstallation meant the system was out of commission during the best months for solar production.
  • Because of the 1951 home’s age, there were some surprises, like a rodent infestation in the back porch that required significant remediation.
  • The new HVAC system generates substantial cooling in the basement utility room, creating some temperature control issues that need to be addressed.
  • Adding a new, airtight, super-insulated roof right on top of the old one took more time because the home had a complex roof that included dormers.

Before & After

BEFORE

AFTER

ENERGY 
CONSUMPTION
BEFORE
173
GJ/year
AFTER
0
GJ/year
COMFORT
BEFORE
Pre-retrofit, the home was drafty and prone to temperature swings that made the basement unusable in the winter and the upper floors unbearably hot in the summer.
AFTER
The home is much more comfortable now, with stable temperatures throughout, even during heat waves and cold snaps.
BUILDING CONDITION
BEFORE
The 70-year-old home was in good overall shape, but did have a maintenance and repair backlog common for a build this age.
AFTER
The home has a brand new roof and exterior, new veranda, completely overhauled HVAC system and an upgraded solar system.
RENEWABLES
BEFORE
Some solar on the house.
AFTER
Upgraded solar system with additional arrays added to the garage.
WAll Insulation
BEFORE
Original 2x4 walls - R10.5 (RSI 1.85) effective
AFTER
Original 2x4 walls with 8" Celluose filled panels - R37 (RSI 6.21)effective
Ceiling Insulation
BEFORE
Original roof construction - R12 (RSI 2.11) effective
AFTER
Original Roof with Framed build up- ~R 52 ( RSI 9.2) effective
Foundation Insulation
BEFORE
Unknown. Possibly ~R8 (RSI 1.4) behind finished portion (90%) basement walls
AFTER
6" GPS, PWF panel support box w R28 (RSI 4.93) Roxul~ R 25 (RSI 4.4) plus orginal
Windows
BEFORE
Mostly dual LowE sliders ~R2.4 (U 2.6) avg. There were also some high-efficiency windows on the main floor.
AFTER
Triple glazed Low E Argon PVC ~ R 4.5 (U 1.26)avg
Ventilation
BEFORE
Bath Fans, Leaky house (3.9 ACH 50)
AFTER
LIFEBREATH 267 MAX HRV (1.1 ACH 50)
Heating
BEFORE
Mid-efficiency gas furnace
AFTER
TOSOT, TU36-24WAWU APEX 3 TON Air Source Heat Pump, TU36-24A/A-D(U) 3 TON A/H 8KW ELECTRIC HEATER
Cooling
BEFORE
None
AFTER
Air Source Heat Pump
Hot Water
BEFORE
Standard gas hot water tank
AFTER
Rheem Hybrid CPROPH80 T2 RH375-15 ASHP water heater
Download Case Study File
Back to Top