Wood Fibre PEER on a Narrow Lot in Canmore



Building Type Single-Family 2+ Stories Location Canmore, AB
Year Built 1993 Foundation Type Concrete (Full Basement)
Structure Type Wood-Framed Post-Retrofit Total Floor Area 174.1m2
Climate Zone 7a Heating Degree Days 5400
Retrofit Status Complete Year Completed 2025
Retrofit Phasing Yes Geometry Changed No
Annual Energy Savings 62.65% Operational Carbon Savings 4.25 tCO2eq/y
Retrofit Type Envelope and Mechanical Performance Level Net-Zero Ready

Project Team

Project Priorities

  • Reduce Energy Consumption
  • Reduce GHG Emissions
  • Improved Resiliency

Upgrades

Envelope Improvements

  • Prefabricated Insulated Panels
  • Attic / Roof Internal Insulation
  • Foundation Walls Exterior Insulation
  • Air Sealing / Airtightness

Mechanical: Heating and Cooling Improvements

  • Air Source Heat Pump – Ducted
  • Condensing Natural Gas or Propane Furnace
  • High Efficiency Wood / Pellet Stove

Mechanical: Hot Water Improvements

  • Tankless / On-Demand Water Heater

Health, Safety & Sustainability Improvements

  • Low-Embodied Carbon Materials

Project Description

The Retrofit Story

This project follows the European building technique called Energiesprong and the Sundance Housing Co-op project in Edmonton led by Butterwick Projects. The retrofit used digital capture technology to develop a 3D model of the home’s exterior, from which the wood fibre Prefabricated Exterior Energy Retrofit (PEER) panels were designed. The first phase of the retrofit featured a mechanical upgrade to a heat pump with gas backup and a tankless water heater with some envelope improvements, while the second phase featured extensive envelope improvements, including walls, windows, doors, attic, and foundation. These panels feature both rigid wood fibre panels and blown-in wood fibre insulation to reduce the system’s embodied carbon. The panels were manufactured off-site and then installed on the exterior of the house on a support mounted to the concrete foundation. The foundation was wrapped in EPS insulation to 18" below-ground level. Blown-in wood fibre as possible was added to the attic on top of existing insulation. Because this neighborhood features narrow lots with houses built right up to the setbacks, we applied for and received a variance to expand the walls 18 percent into the setback setting a precedent for future retrofits on narrow lots.

Lessons Learned

Windows

The windows took longer to install than we expected. Due to the close proximity to the side setback and fire code the glazing had to remain at its original location, we could not place them completely into the panel. This created detailed work on the interior and exterior jambs which took longer than we had hoped.

Phasing

When the homeowner completed the first intervention on this project, an interior renovation with mechanical upgrades, they were not considering adding exterior insulation to the walls and foundation. This led them to install a heat pump with a high efficiency gas backup to meet the heating loads. Later, when the exterior retrofit was completed the heating demand was reduced significantly. It may have been possible to install a smaller unit to meet the demand (saving some money and complexity on the system) or with an all electric system which would provide a clearer path to reduce their GHG emissions more and potentially remove the gas line completely.

Adjacent buildings

Although the occupants of adjacent buildings were supportive, which was crucial for obtaining municipal permission to build in the setback, the narrow lots and proximity of neighboring buildings presented challenges. Work regularly occurred on, and scaffolding extended into the sides of adjacent properties. While the sides of these lots are often unused or unlandscaped, they became construction sites and siding was damaged on one occasion.

Before & After

Envelope

Mechanical & Electrical

Annual Energy Usage

Carbon Emissions