1954 bungalow goes net-zero ready with a groundbreaking panelized deep retrofit.
This home was one of North America's first three single-family homes to get a panelized deep retrofit. The project transformed the 70-year-old house into a high-performance building.
No items found.
No items found.
Edmonton, Alberta
Inspired by a Netherlands green building technique called EnergieSprong, the retrofit used digital capture technology to develop an exact 3D model of the exterior of the 1,120-square-foot home. Peter Amerongen, one of Retrofit Canada's co-founders and a partner at Butterwick Projects, used the 3D model to size the prebuilt, airtight panels for a perfect fit.
The panels were manufactured off-site and then installed on the outside of the house, resting on an insulated panel support box designed to take the weight of the panels. After securing the panels to the support box at the bottom and the eaves at the top, crews framed a new roof right over the old one, making the house airtight, super-insulated and so efficient it can get all of its annual power needs from renewables.
The building is an example of a 1950s house built high out of the ground so that the basement would be more useful, a less common feature at the time. The more elevated basement meant the project required less excavation. But compared to the two other projects that were part of the same demonstration project, the panel support box, which runs along the seam where the concrete foundation meets the main floor, was much taller.
The home is now net-zero-ready.
In the future, the owners plan to add solar to the house and garage, making the home emissions-free with enough capacity for an electric vehicle.
Challenges
Back porch The home’s back porch rested on piers instead of the basement foundation and the family wanted to retain the storage space under the porch. Maintaining insulation and air tightness around and under the porch required some nifty detailing that can be seen in the drawings.
Basement suite Another aspect of the project was its fully-finished basement suite. While the family currently uses the whole house, they want the option to rent out the basement as a legal suite after their kids leave home. Accommodating the basement suite required additional planning to install two separate HVAC systems that comply with building code. It also meant finding paths for the intakes and exhausts for the two HRVs without making duct runs too long and windy.
New roof There were three considerations that led to the choice of a new scissor truss roof over the existing one. The existing roof overhang was too short to accommodate the increase in wall thickness resulting from the panels. The attic had vermiculite insulation that likely included small amounts of asbestos, meaning costly remediation would be needed before the attic could be air-sealed and reinsulated. The owners wanted to change the roofline for aesthetic reasons anyway. Given these factors, it made more sense to use scissor trusses to frame and insulate a new airtight roof right over the old one.
Heat Pump installed before insulation complete Because the original block chimney needed to be removed to accommodate the HRV ducting, the new heat pumps were installed before crews finished making the house airtight and fully insulated. Because this happened in the dead of winter, the owners spent a lot of money heating the home, which only had its original insulation and poor airtightness.
What went well
Panel Installation Like other panelised retrofits Butterwick Projects has done, the panels fit perfectly, proving the panelisation works.
Insulating the basement As the home needed new weeping tile anyway, installing the foundation insulation on the exterior was a piece of cake. The foundation was already excavated.
Previous experience with panelization As this project was the builder’s third panelized retrofit, it benefited from the learnings of the first two.
VIDEO - PANEL FLY-IN
Construction Activities
Pre-panel installation:
Use trench previously dug around the house for weeping tile replacement to add a waterproofing membrane and insulation to the foundation.
Install a “drainage” layer of insulation with vertical grooves resting right against the foundation and a second layer of EPS foam insulation (combined total of 5.5” of insulation).
Install the HRV Ducting in the attic via the old chimney chase to serve the main floor bathroom and kitchen.
Install high-efficiency Heat Recovery Ventilators that provide a continuous supply of healthy fresh air.
Replace the gas furnaces and hot water tanks with Air Source Heat Pumps and disconnect the gas line. (The home already had a legal basement suite with separate HVAC from the main floor).
Install a pressure-treated panel support box, called a boxbeam, with penetrations for new HRV, air source heat pump, and existing services. Insulate the boxbeam with two to three inches of low Global Warming Potential spray foam insulation that provides an air-barrier seal between the foundation and the WRB on the panels. Fill the remainder of the cavity with Roxul insulation (approximately R28).
Loosen the existing windows.
Install the tie-back blocks that the panels will be attached to.
Demolish and remove the old concrete chimney. The cavity was used for running HRV ducting to the main floor bathroom and kitchen.
Cut off the existing roof overhang and install a flap of WRB under the existing shingles to prevent precipitation from getting into the new wall cavity.
Wrap the roof in a poly vapour barrier and seal it to the WRB flap.
When the panels were built and delivered, Butterwick crews worked with a crane operator to install them. All the panels were installed in less than a day and fit beautifully within the design tolerances. The new high-performance windows were factory-installed in the panels. Doing this in a controlled environment results in bullet-proof installation that enhances long-term durability.
Post-panel installation:
Secure the panels using the pre-installed tie-back straps.
Blow in cellulose insulation (R28) for new panels.
Seal the WRB flap protecting the cavity behind the wall panels to the top of the wall panel.
Seal the water-resistive barrier (WRB) from panel to panel and the panel support box.
Install a new truss roof over the existing roof.
Blow in attic insulation before the roof is shingled (R50)
Shingle the roof.
Make a continuous air seal between the roof poly and the panels' water-resistant barrier.
Interior finishing around windows and doors
Exterior finishing - new siding, facia and soffits
Funding Sources
Funded in part for innovation by SSRIA
Before & After
BEFORE
AFTER
ENERGY CONSUMPTION
BEFORE
165
GJ/year
AFTER
55
GJ/year
COMFORT
BEFORE
Older home. Inconsistent temperatures and drafty.
AFTER
Consistent temperatures throughout the home. Way more comfortable.
BUILDING CONDITION
BEFORE
Typical for a 1950s structure.
AFTER
Looks brand new, will not require maintenance for years.
RENEWABLES
BEFORE
None
AFTER
To be installed at future date. Now that the home is net-zero ready (approximately 80% more efficient), it can get all of its power from a renewable source like solar. The building has sufficient roof area for solar to meet all annual energy needs.
WAll Insulation
BEFORE
R14
AFTER
The new wall panels added an additional R25 (Effective) for a total of R40.
Ceiling Insulation
BEFORE
R50
AFTER
The additional R55 in the new scissor truss attic brings the total to over R100 (Effective).
Foundation Insulation
BEFORE
Exterior Foundation - None, Foundation Header - R14
AFTER
Above grade - R39, including additional R25 in the panel support box. Below grade - R33 (Effective), with additional R19 GPS insulation.
Windows
BEFORE
Vinyl sliders. U factors ranged from 1.5 to 5.1. R values ranged from R1.1 to R3.9
AFTER
New high-performing windows with U factor of 0.8 and R6.7 insulation.
Ventilation
BEFORE
None
AFTER
Two VanEE V160E75RS ERVs (Heat Recovery Ventilators that recover heat and moisture from outgoing airstream).
Heating
BEFORE
Two natural gas furnaces
AFTER
Two Air Source Heat Pumps (TOSOT 2TON TU36-24WADU)
Cooling
BEFORE
None
AFTER
Two Air Source Heat Pumps
Hot Water
BEFORE
Natural gas storage tank with pilot, .55 efficiency.
AFTER
Integrated heat pump, 3.75 Uniform Energy Factor (UEF)